2024 Main Street Restoration Project

7-19-24 Project Update

July 20, 2024

Project cleanup has been the theme over the course of the week after sliding the barricades late last week. Over the course of the week, Ottertail Aggregate has been working on boulevard grading and topsoil placement in Phases 2 and 3, as well as filling in additional aggregate material behind the concrete driveways that were…

Asset 1pavingperham

Note: information below is tentative and subject to change at any time during construction process.

Phase #1a

Main Street from 1st Ave S to 5th Ave SW

Business landmarks: Lakes Home Outlet/North Threads to Back in Motion Physical Therapy

Tentative timeline = Phase complete, corners will be completed when phase 1b and phase 4 are in construction.

Phase #2

6th Ave SW to 4th Ave SW 

Business landmarks: Esser's/Perham Police Dept./Perham Fire Dept. to People Ready/Papacitos/Mobil

Tentative timeline: current-early/mid July

Phase #3

Lakeside Drive/Hwy 34/Hwy 51 to 6th Ave SW

Business landmarks: Schmitz Motor Co/Northwoods Life Church to Esser's/Perham Police Dept./Perham Fire Dept.

Combined with Phase #2.

Tentative timeline: current-early/mid July

Phase #4

4th Ave SW through 1st Ave S intersection

Business landmarks: People Ready/United Community Bank to Photo Magic/The Back Porch

Start date: Mid August.

Full Depth Reclamation

Main Street/County 80 from Hwy 10 to Hwy 10

Final step to be completed this fall.