2024 Main Street Restoration Project

5/3/24 Project Update

May 4, 2024

R.L. Larson’s two construction crews continue to work on the underground utility replacement in Phase 1, completing the replacement of the sanitary sewer mains yesterday. On Thursday afternoon, one of the crews also stubbed the sanitary sewer main out of Main Street north on Second Avenue Northeast in advance of Phase 1B, which will occur…

Asset 1pavingperham

Note: information below is tentative and subject to change at any time during construction process.

Phase #1a

Main Street from 1st Ave S to 5th Ave SW

Business landmarks: Lakes Home Outlet/North Threads to Back in Motion Physical Therapy

Tentative timeline = end of April to beginning of June

Road Detour signs will be placed 4/17/24, find updated detour routes at the map link above.

Phase #2

6th Ave SW to 4th Ave SW 

Business landmarks: Esser's/Perham Police Dept./Perham Fire Dept. to People Ready/Papacitos/Mobil

Phase #3

Lakeside Drive/Hwy 34/Hwy 51 to 6th Ave SW

Business landmarks: Schmitz Motor Co/Northwoods Life Church to Esser's/Perham Police Dept./Perham Fire Dept.

Phase #4

4th Ave SW through 1st Ave S intersection

Business landmarks: People Ready/MirrorMirror Salon to Photo Magic/The Back Porch

Tentative start after summer

 

Full Depth Reclamation

Main Street/County 80 from Hwy 10 to Hwy 10