7-19-24 Project Update

By marketing@perhamcc.com | July 20, 2024

Project cleanup has been the theme over the course of the week after sliding the barricades late last week. Over the course of the week, Ottertail Aggregate has been working on boulevard grading and topsoil placement in Phases 2 and 3, as well as filling in additional aggregate material behind the concrete driveways that were…

7-12-24 Project Update

By marketing@perhamcc.com | July 12, 2024

Central Specialties and Ottertail Aggregate have been working on Phases 1, 2 & 3 throughout the week. Early in the week, Central Specialties finished the second lift of pavement on Phases 2 and 3. Ottertail Aggregate worked on all three phases, cutting existing pavement and preparing the subgrade for tie-ins to driveways and parking lots.…

Turtle Race Park Mural

By marketing@perhamcc.com | July 9, 2024

Turtle Race Park Mural Located in City Hall/Turtle Race Park on the wall of Ottertail Glass, located at 147 East Main Street

Waves of Discovery Mural

By marketing@perhamcc.com | July 9, 2024

Waves of Discovery Mural Located on 1st Ave N on the wall of Photo Magic, located at 102 West Main Street Fun Facts and Hidden Objects This piece was inspired by the artists love for growing up in Perham, the heart of the Minnesota lakes area. It was created with a medium of carved concrete…

Welcome to Perham Mural

By marketing@perhamcc.com | July 9, 2024

Welcome to Perham Mural Located in NP Park on the wall of MN Tru North, located at 200 West Main Street

7-3-24 Project Update

By marketing@perhamcc.com | July 7, 2024

With the shortened work week, construction has been limited to a few of the subcontractors on the project. On Monday morning, Central Specialties began the construction of the first course of bituminous pavement on Phases 2 & 3. The two-inch course of pavement was constructed over the course of Monday and Tuesday morning along with…

6-28-24 Project Update

By marketing@perhamcc.com | June 28, 2024

Progress continues along Main Street with activities primarily focused on Phases 2 and 3. On Monday, Knife Lake Concrete arrived in town and has placing concrete all week. Over the course of the week, they have constructed sidewalk and driveways working their way west from Fourth Avenue West toward the intersection of County Highways 34…

6-21-24 Project Update

By marketing@perhamcc.com | June 24, 2024

Although the rain early this week slowed some of the construction activities on the project, the concrete crew was still able to begin constructing the curb and gutter on Phases 2 and 3 starting yesterday. Ottertail Aggregate has been the busiest subcontractor in town over the course of the week, with boulevard grading occurring east…

6-14-24 Project Update

By marketing@perhamcc.com | June 14, 2024

What a change in eight weeks! This week Phase 1 was opened to traffic for the Turtle Fest activities. In the past eight weeks, R.L. Larson and their crew of subcontractors completed the utility replacement and the majority of the surface improvements through the first four blocks of the project, allowing the phase to be…

6-7-24 Project Update

By marketing@perhamcc.com | June 7, 2024

With three phases of construction underway, activities are occurring on all ends of Main Street. On the west end of Main Street, R.L. Larson is nearing completion on the watermain replacement from Seventh Avenue to the intersection of County Highways 34 and 51. Early this week, they made a tie-in to the existing watermain beneath…