Skip to content

Blog

Crazy Dayz

By marketing@perhamcc.com | June 2, 2024

August 2-3, 2024 More info here! Follow PerhamEvents on Back to Community Events

5-31-24 Project Update

By marketing@perhamcc.com | June 1, 2024

A shortened week with the holiday and the rains have slowed some of the improvements on Main Street, but the number of crews working in town has allowed the project to progress. Over the course of the week, R.L. Larson, Ottertail Aggregate, Parsons Electric, Aqua Lawn, Central Specialties, and Knife Lake Concrete have all been…

5-24-24 Project Update

By marketing@perhamcc.com | May 25, 2024

Rain, rain, go away… Although work has progressed on Main Street over the course of the past week, the rain has impacted some of the activities that were planned to be completed. Early this week, Knife Lake Concrete worked on the installation of sidewalk on the easterly portion of Phase 1 (Third to Fifth Avenue)…

5-17-24 Project Update

By marketing@perhamcc.com | May 18, 2024

Over the course of the past week, work has continued on Phases 1 and 2 on the Main Street Project. On Phase 1, Ottertail Aggregate has completed the last of the removals of sidewalk and pavers and has been hauling aggregate to the site preparing for the upcoming concrete and bituminous pavement improvements. Knife Lake…

5-10-24 Project Update

By marketing@perhamcc.com | May 10, 2024

Even with the rain early this week, construction has continued on Main Street. R.L. Larson’s two construction crews finished the underground water, sewer, and storm sewer on Phase 1. Yesterday, one of the crews shifted to Phase 2, the portion of Main Street from Fourth to Sixth Avenue West. The crew started the sanitary sewer…

5/3/24 Project Update

By marketing@perhamcc.com | May 4, 2024

R.L. Larson’s two construction crews continue to work on the underground utility replacement in Phase 1, completing the replacement of the sanitary sewer mains yesterday. On Thursday afternoon, one of the crews also stubbed the sanitary sewer main out of Main Street north on Second Avenue Northeast in advance of Phase 1B, which will occur…

4-26-24 Project Update

By marketing@perhamcc.com | April 26, 2024

Construction is underway on Main Street and moving quickly. On Monday morning, removals started at the intersection of Third Avenue East and Main Street and worked to the west toward First Avenue. The existing pavement, curb and gutter, trees grates and lights were removed early this week, with completion near the intersection of First Avenue…

4-19-24 Project Update

By marketing@perhamcc.com | April 20, 2024

Activity has started on Main Street throughout the week as outlined in the last update. Early in the week, some of the signage on Highway 10 directing Truck Traffic away from downtown was setup, with final Traffic Control and Detour signage for the first phase going up on Wednesday. Some of the road closures and…

Holiday Parade of Lights

By marketing@perhamcc.com | April 17, 2024

November 29, 2024 Back to Community Events

Home for the Holidays

By marketing@perhamcc.com | April 17, 2024

Black Friday-Christmas Eve, 2024 Click Here Back to Community Events

Scroll To Top